Eliot Street between Prospect and Chestnut Street - Road Construction

Construction

Road Construction on Eliot street between Chestnut Street and Prospect Street - installing a Sewer line.

Patriot Excavation will perform the work.  All Abutters have been notified.

The hours of work will be from 7 a.m. till 5 p.m., Monday through Friday.  The work will involve closing Eliot Street for the hours of 7 till 5 on each day of construction.  Police details have been set up for the project.

This approved road project will take approximately 2 weeks, weather permitting.  Below is a schedule detailing the milestone goals for each week.

Week of July 2nd 
Monday
Put up electronic sign board
Week of July 9th 
Cut pavement core existing manhole, Install sewer and first sewer manhole, Install sewer main and complete sewer road work and pave road
Week of July 16th

Expose water main and plate for night, Cut water main install 3 way gate valves and backfill and
Complete water line work and pave a patch on edge of road

Misc. Cleanup and breakdown of signage.