General comment:
The site contractors are aware of critical times during the day when traffic to the train station is high and will make all efforts to not adversely impact or delay commuters. Please expect delays and plan accordingly. Traffic traveling into the station in the morning is a priority over traffic leaving the station. One lane will remain open during construction.
Week ending 3/3/2017 construction activities:
The roadway contractor continued installation of the sewer from the ball field toward the RTD site. All trenches have been paved. Eversource gas did not work all week.
Next week (3/6 - 3/10) construction activities:
The roadway contractor will finish installing sewer on Monday having reached the RTD site. Tuesday the water main construction will begin at the Dunkin Donuts driveway installing the 12 inch water main toward the train station. At this time, Eversource has not indicated that they will be working in the roadway next week.