[ARCHIVED] West Union Transmission Sewer Replacement - Project Status

June 16

Contractor has completed the Christy Lane top course pavement work.

The Contractor has scheduled the Brook Street paving work for Monday and Tuesday June 19 & 20th. The work will include removal of the pavement, edge of road to edge of road on Monday. The Contractor will return Tuesday to install binder pavement from edge of road to edge of road in Brook Street to the beginning of Columbus Avenue.

To facilitate this paving work the Contractor will close Brook Street off to vehicle traffic at 8:00 am on Monday and Tuesday, as the roadway width is too narrow to safely allow vehicle traffic at all times throughout the day. The Town is requesting that you park your car(s) on Columbus Avenue prior to 8:00 am, if you need to leave Brook Street during the day. The roadway should be open to traffic by 3:00 pm.

If the work is not completed on Tuesday the Contractor will mobilize Wednesday morning around 7:00 am and close the road at 8:00 am and complete the binder installation.

Once the pavement is installed the road will remain closed to vehicle traffic for a minimum of one (1) hour to allow the pavement to cool, to prevent “rutting” by cars. The top course pavement and driveway aprons will be completed at a later date. The same work will be scheduled for Columbus Avenue once the Gas Company completes their work.

Gas company anticipates completing the gas main installation next week.

If you have any questions you can contact the DPW at (508) 881-0120 or Gregory Eldridge from Haley and Ward Inc. at (978) 648-6025. Haley and Ward is the engineering firm contracted by Ashland to oversee the project. Alternatively, Haley and Ward sends updates through emails. If you prefer communications through email, please send an email, with your street address, togeldridge@haleyward.com , with a subject line “West Union Sewer Update”.

June 14,

 Gas company is closing in on completing the new gas main installation on Columbus. It appears they have started connecting services to the new main and should complete the project early next week.

ME Smith completed the top course paving on Clyde this afternoon and will mobilize to Christy tomorrow. They will return to repair the lawn areas on Clyde.

ME Smith was delayed in completing the paving work on Clyde today. Due to the delay they did not mobilize to Christy and start the paving work. They will mobilize tomorrow morning and close the road at 8:00 am, as previously mentioned any Christy residents that need to leave during the day, please park your car on Metropolitan before 8:00 am.

June 13,

 Contractor is continuing the paving restoration work on Clyde Street today. He anticipates completing the top course pavement in Clyde tomorrow morning.

Wednesday morning after completing Clyde paving work, the Contractor will mobilize to Christy around 10:00 am to complete the top course paving work. The Contractor anticipates closing Christy to vehicle traffic around 11:00 am, please park on Metropolitan if you need to leave the street after 11:00 am.

Any questions please do not hesitate to contact me or the Town.

Loam and Seed: Contractor has completed some loan and seed work along the project. We will review the entire project and identify areas that required attention.

Finish Road Restoration: Permanent paving work will be completed during the spring/summer season. This will allow settlement in the trenches, if any, to occur before finish paving.



Here is the progress from the past weeks.