[ARCHIVED] West Union Transmission Sewer Replacement - Project Status

West Union Project update 11-4-16

The contractor completed the sewer main and water main installation in Clyde last week. Water main testing remains, once completed, water services will be connected to the new main and the bright blue temporary water main will be removed. The Contractor began sewer replacement in Christy Lane and is close to Metropolitan intersection.
On Monday 11-7-16 the Contractor will be paving in Main Street. One lane traffic will be maintained throughout the work and will be completed Monday.
Contractor has scheduled the sewer replacement in Metropolitan for next week. Due to the narrow width of the roadway, vehicular traffic will see delays. Work in Metropolitan is scheduled for Monday through Thursday.
Work in Metropolitan will extend from Christy to the emergency access road to the Ashland Commons site. If you have any questions or need special provisions please do not hesitate to contact the Engineer by email (geldridge@haleyward.com), or speak to the contractor at the site.

Here is the progress from the past weeks.